- Monday, 29 December 2014
- Written by istafer
Type : |
PC |
Client : |
PIDMCO (Petrochemical Industrial Management Co.) |
Project Title : |
Procurement, Construction and equipment Installation of Bandar Emam Petrochemical complex |
Status : |
Completed |
Description : |
All civil works such including sit preparation, landscaping, Concrete paving and all industrial civil works including equipment and storage tanks foundations, concrete trenches, duck banks, pipe rack concrete super structure, all Heater, exchanger, cooling tower, compressor super structures and condensation towers super structures. Carbon-Steel and HDPE piping including shop welding, beveling, fit up, surface sand blast, primer, wrapping and all related tests. |